Descrierea proiectului

From April 2013 the water quantity produced by the wells started to drop. The missing quantity was supplied from the grid. This trend led to shutting down even the last well in October
2013. Since then, the meat plant has been meeting its water demand exclusively from the grid.

During the recommissioning the main problem to be solved was the high concentration of iron, manganese, and ammonium in two of the three wells, and the high arsenic content in one well. In addition, water in all three wells has a high Na content.

Detalii

Obiectul contractului:

Recommissioning the existing wells, design and construction of a new facility
Locație:
Szolnok, Hungary
An:
2014

Caracteristici

Recommissioning three existing wells and the design and construction of the new water treatment facility (1,920 m2 including the area of the wells, water treatment facility, storage tank, and water tower)

Imagini ale proiectului

Alte proiecte

Locație: Kecskemét, Hungary
An: 2009-2024
We were involved in the preparation of permit, construction, installation and implementation plans for WERK1-2 projects, as well as site engineering tasks.
Locație: Kecskemét, Hungary
An: 2013
Complete building engineering: comfort ventilation and extraction systems.
Locație: Uppsala, Sweden
An: 2006
3D design of pharmaceutical technology plant, using the MicroStation TriForma and Bentley Plant Space Design Series software